The first of the new two-lane bridges being built across the Waitaki River between Kurow and Hakataramea, is taking shape.

The New Zealand Transport Agency’s (NZTA) project manager Steve Proud said the construction of the bridge, which is being built over the southern branch of the river, remains on schedule.

“Piling is now completed and work has started on concreting the bridge columns and the abutments,” he said.

“Work will begin mid-next month driving the 11 piles for the second bridge on the Hakataramea side of the river.

“This work will take until mid-March to complete.”

 

Pick up a copy of the Oamaru Mail for the full story…

We’re currently offering a special subscription offer for website browsers of $4.50 a week for the Oamaru Mail to be home delivered for a minimum of 3 months.

Call Kathy or Diane on 433 0521

Oamaru Mail – Customer Service Team

– New subscriptions – Subscription Payments – Delivery issues – Any other queries relating to your subscription

Tel: 03 433 0521

Phone lines are open 8.30am to 4pm weekdays.